Paving operations on Boulder county roads began on Tuesday, July 12. Operations will run from 6:30 a.m. to 4:30 p.m., Monday through Thursday, and is expected to last until the end of August. Below is the list of road segments that will be paved (in order):
- 79th Street between CO Highway 52 and Niwot RoadÌý
- Monarch Road between 79th Street and the Diagonal HighwayÌý
- 73rd Street between the Diagonal Highway and Niwot RoadÌý
- Niwot Road between the Diagonal Highway and 73rd StreetÌý
- 63rd Street between Jay Road and the City of Boulder limitsÌý
- 2nd Avenue in NiwotÌý
- Valmont Road between Boulder Creek and 61st StreetÌý
Work on each segment is expected to last one week, other than 2nd Avenue which should require two to three days. Flaggers will help guide travelers safely through construction zones, but expect delays and please drive with caution. Avoid construction zones if possible; click on the article title to see a map.